From prototype to series production: the stages of industrialisation

Contents

The main stages, from idea to series production

Industrialising means moving from one working unit to repeatable production, with controlled cost and quality. The typical path has six stages, which sometimes overlap:

  1. Scoping: function, constraints, target volumes, target cost, applicable regulations.
  2. Mock-up: validate shape, size and ergonomics.
  3. Functional prototype: validate real-world operation.
  4. Design for manufacturing and choice of series processes.
  5. Tooling and pre-series: make the tooling (moulds, cutting tools, jigs) and produce the first parts with the series process.
  6. Qualification and series launch.

The first three stages cost little and are easy to redo; the later ones commit investments that are hard to recover. The earlier a mistake is found, the less it costs: that is the whole point of prototypes before tooling.

What to decide at the scoping stage

Set the annual volumes you expect, the product’s lifespan, the target cost per part, the standards or regulations of your sector and the dimensions that are truly critical. For each stage, also define what will allow you to decide to move on to the next: without written success criteria, a prototype proves nothing and iterations follow one another endlessly.

Mock-up and functional prototype: what to validate at each stage

The mock-up

It does not need to work. It is used to judge shape, size and handling, and to discuss them with stakeholders. It is made from substitute materials, most often by 3D printing, with foam, wood or cut parts: it is quick and inexpensive.

The functional prototype

It checks real behaviour: mechanical, thermal, sealing, assembly. It is made by CNC machining, laser-cut sheet metal or 3D printing, depending on the part. When the function depends on the material, choose a process close to the series one: a prototype printed in resin does not behave like a part injection-moulded in polyamide. To weigh up processes, see our comparison 3D printing or CNC machining.

Write down before manufacture what this prototype must demonstrate and how you will measure it. Plan for several iterations, and remember that a single part carefully machined does not prove that the series will hold the same tolerances. A prototyping workshop can help you frame these first trials.

DFM and DFA: designing for manufacture and assembly

DFM (design for manufacturing) adapts the design to the series process; DFA (design for assembly) makes assembly easier. A few reflexes depending on the process:

  • Machining: internal radii compatible with milling cutters, shallow pockets, tight tolerances limited to functional dimensions.
  • Sheet metalwork: uniform bend radii, holes kept away from bends (see the guide to laser cutting and bending).
  • Plastic injection: even wall thicknesses, draft angles, ribs rather than thick sections.
  • Assembly: fewer parts, standard fasteners, symmetrical shapes or poka-yoke features, access for tools.

Involve the manufacturer early. A design review by the workshop or by a design office before the drawing is frozen costs little compared with the price of modified tooling. It is often the best saving in the project.

Choosing processes according to volumes

As quantity rises, investing in tooling to reduce unit cost becomes worthwhile. The break-even point is simple to calculate: tooling cost divided by the saving made on each part. Thresholds vary a lot from one part to another; this table gives the general logic.

VolumeUsual processesEconomic logic
One to a few parts3D printing, CNC machining, laser-cut and bent sheet metalNo tooling: high unit cost, almost no investment.
A few dozenMachining, sheet metalwork, 3D printing, vacuum casting in silicone mouldsSilicone moulds allow small runs of plastic parts.
Hundreds to thousandsSheet metalwork with simple tools, machining with dedicated fixtures, injection moulding in aluminium mouldsModerate tooling, recouped fairly quickly.
Large seriesInjection moulding in steel moulds, stamping, bar turning, castingCostly tooling, very low unit cost.

For plastic parts, see the plastics processing expertise page. Ask for quotes at several quantities: the price curve shows where tooling becomes worthwhile.

Finally, watch the continuity of material and process. A part prototyped in machined aluminium and then produced by casting, or printed and then injection-moulded, has neither the same structure nor the same tolerances: repeat the key tests on parts made with the series process.

Tooling and moulds: an investment to scope carefully

Injection moulds, cutting or stamping tools, welding jigs, machining fixtures, inspection gauges: tooling is often the first investment item and the slowest to obtain. Three points deserve to be settled from the outset.

  • Correction margin. After the first trials, the tool almost always needs correcting. It is easier to remove material than to add it: toolmakers often machine first with a little extra material left on.
  • Expected tool life, which depends on the tool material and the material being processed: state your total volumes so that the toolmaker sizes the tool accordingly.
  • Ownership and custody. Who owns the tool you finance? Where is it stored, who maintains and insures it, on what terms is it returned to you, can it be used for another customer? These points are settled in writing, in the quote or the contract. See our guide to protecting drawings and tooling.

Not everything requires heavy tooling. For modest volumes, modular fixtures, machining set-ups or 3D-printed jigs often avoid an investment that would never be recouped.

Pre-series and qualification: FAI and PPAP

The pre-series

This is a small run made with the final tooling and process. It checks production capability, assembly, cycle rates and inspection, and often supports validation tests (environmental, endurance).

First article inspection (FAI)

A first article made with the series process is fully inspected: every characteristic on the drawing is measured, materials and certificates are checked, and everything is recorded in a report. This inspection is formalised in aerospace (standard EN 9102).

PPAP

Originating in the automotive industry, PPAP is an approval file for the production process. It demonstrates that the process repeatedly makes conforming parts: drawings, dimensional results, materials, control plan, risk analyses.

These frameworks apply only if your sector or your end customer requires them. In other cases, a dimensional report on the first batch and a simple control plan are often enough. A laboratory or an inspection and metrology workshop can carry out these measurements.

Typical schedule and milestones

Durations vary enormously: rolling out an existing machined part takes far less time than creating a moulded product. These orders of magnitude mainly show the sequence.

StageIndicative duration
Scoping and specificationa few days to a few weeks
Mock-upa few days
Functional prototype (per iteration)a few days to a few weeks
Design for manufacturing, supplier selectiona few weeks
Tooling (mould, cutting tool)several weeks, sometimes several months
Tool trials and correctionsone to several loops
Pre-series and qualificationa few weeks, depending on the framework

The critical path almost always runs through tooling. Launch the purchasing of specific materials and the preparation of inspection in parallel.

To shorten the schedule, limit the number of iterations with a good design review, if possible choose a partner able to make both the prototype and the series, and allow a margin for tooling corrections rather than a schedule with no contingency.

Pitfalls to avoid

  • Freezing the design too early, or too late. Too early, you lock in flaws; too late, you delay the tooling.
  • Validating with an unrepresentative prototype: material, process or tolerances different from the series.
  • Underestimating tool tuning and its correction loops.
  • Forgetting ancillary costs: inspection, packaging, logistics, certification.
  • Changing supplier between prototype and series without passing on the know-how: up-to-date drawings, revision indices, inspection reports.
  • Leaving rights over drawings and tooling unclear.
  • Ignoring uncertainty over volumes: a bridge production in small runs avoids investing too early.

One project, several possible suppliers. On Meaflow, you can post a request for your prototype, with several quantities. Posting is free and commission-free, and you compare quotes from several suppliers. To write your request, see the specification guide.

Frequently asked questions

What is the difference between a prototype and a pre-series?

A prototype validates an idea or a function, often with processes different from the series. A pre-series is a small run made with the final tooling and process, to check that industrial production meets the requirements before launch.

From what quantity should I invest in a mould?

There is no single threshold. You compare the tooling cost with the saving made on each part: the simpler the part and the higher the volume, the more the tool is justified. Ask for quotes at several quantities with and without tooling to see the break-even point.

What is a PPAP and do I need one?

PPAP is an approval file for a production process, which originated in the automotive industry. It is only necessary if your customer or sector requires it. Otherwise, an inspection report on the first batch and a simple control plan are often enough.

Can I change supplier between prototype and series?

Yes, it is common, because not every workshop is suited to both phases. Pass on up-to-date drawings, inspection reports and lessons learned, and make sure the tooling and the rights over the drawings are clear in writing.